A rehab budget should separate three exposures: repairs that a lender may require before delivering a loan, as-is work that affects value or the exit but does not trigger a required repair under applicable Fannie Mae guidance, and statutory lien risk created by hiring labor or suppliers. The dividing line for the first two is whether a deficiency could affect safety, soundness or structural integrity. Georgia lien rights are a separate issue and can attach to the property.

Why the safety, soundness and structural line matters

This is a scope decision, not a cosmetic-versus-structural checklist. Under Fannie Mae Selling Guide B4-1.3-06, condition ratings C1 through C5 may be eligible in as-is condition. C6 indicates deficiencies severe enough to affect safety, soundness or structural integrity. A loan secured by a C6 property is not eligible for sale to Fannie Mae until those deficiencies are repaired to at least C5. If any part of the dwelling is C6, the whole dwelling receives a C6 rating.

These are Fannie Mae delivery requirements, not law and not universal lender rules. A lender’s requirements depend on its loan program and underwriting. For background on the separate appraisal and value issues, see GPC Real Estate’s Atlanta appraisal and refinance guide.

What can force a “subject to” appraisal

When an appraiser identifies a deficiency that could affect safety, soundness or structural integrity, Fannie Mae B4-1.3-06 calls for an appraisal “subject to” completion of the specific repairs or alterations. The ratings then reflect the hypothetical condition that the work is complete.

Fannie Mae B4-1.2-05 lists examples for existing construction, including foundation settlement, water seepage, active roof leaks, worn roof shingles, inadequate electrical service and inadequate plumbing fixtures. These items must be completed and verified before the loan is sold to Fannie Mae. Infestation, dampness or abnormal settlement also require a comment on the effect on value and marketability. The lender must then show correction or submit a professionally prepared report that the condition does not threaten structural damage.

If the appraiser is not qualified to evaluate a repair, the appraisal may be subject to an inspection by a qualified professional. The lender decides whether the inspection is required and whether the property is eligible. The appraiser is not automatically required to review that report, reinspect, or provide Form 1004D in this situation.

What is reported as-is, and what it can cost

Minor conditions and deferred maintenance that do not affect safety, soundness or structural integrity are reported and reflected in the as-is opinion of value. Fannie Mae B4-1.3-06 gives worn floor finishes or carpet, minor plumbing leaks, holes in window screens, missing handrails and cracked window glass as examples. The qualification matters: the condition must not rise to the safety, soundness or structural threshold.

An as-is item can still reduce marketability, require a later repair or weaken a refinance plan. The lender may escrow for minor items at its discretion, but an escrow does not turn them into mandatory repairs under the cited rule. For comparable-sale analysis, see how to pull Atlanta comps when sources disagree. For refinance sensitivity, see where Atlanta BRRRR math can break.

Completion paperwork that belongs in the budget

Fannie Mae generally requires improvements, alterations and repairs on the subject property to be complete when the loan is sold. Form 1004D, the Appraisal Update and/or Completion Report, may use an on-site visual inspection or acceptable alternatives such as virtual inspection, digital photographs or site video. Exhibits must be visually verifiable, unaltered and authenticatable using metadata and the subject property’s geocode.

For certain repairs to existing construction, Fannie Mae also permits a borrower attestation letter. It must identify the borrower and property, certify satisfactory completion, be signed and dated, include visual exhibits, and include one of the following: a qualified professional’s signature, a professionally prepared report or paid invoices.

The cited guide does not assign the cost of a reinspection to a particular party. The lender determines acceptable verification, and the borrower should confirm any inspection, documentation and payment responsibilities with the lender and relevant contract parties before work begins.

The 10% and 120% figures are not rehab rules

Fannie Mae’s postponed-improvements route applies to new or proposed construction, not ordinary repairs to existing construction. Under B4-1.2-05, qualifying postponed items must be completed within 180 days of the note date, be part of the sales contract, be postponed for a valid reason, and not prevent an occupancy permit. Their cost cannot exceed 10% of the as-completed appraised value. The lender establishes an escrow equal to 120% of estimated completion cost, or the full fixed-price contract where the builder offers a guaranteed fixed-price contract.

These limits do not create a 10% allowance or a 120% holdback rule for a rehab on existing construction.

Georgia licensing and the lien attached to the property

Georgia’s residential contractor definition generally covers compensated residential-basic or residential-light-commercial work when the total value of the work or compensation, whichever is higher, exceeds $2,500. The categories have scope limits. Electrical, plumbing and certain other trade work may require separate licensing. See O.C.G.A. § 43-41-2.

Under O.C.G.A. § 43-41-17, a contract for work requiring a license, made with a contractor who was not properly licensed at the legally specified date, is unenforceable by the unlicensed contractor. In that circumstance, the unlicensed contractor has no lien or bond claim for work under that contract or its amendments. The statute has exceptions. For example, the repair-work exemption requires disclosure of unlicensed status and does not cover work affecting structural integrity. A permit applicant for licensable work must provide the required license information under O.C.G.A. § 43-41-14. Contracting without complying with the licensing chapter can also be a misdemeanor under O.C.G.A. § 43-41-12.

The owner-builder exemption is not for rentals

The owner-builder exemption in § 43-41-17(h) is limited to a building intended solely for occupancy by the owner and the owner’s family, firm or corporation and its employees. It cannot be used for a building offered for sale or lease or intended for the general public. The statute also restricts repeat self-build sales within a 24-month period after a certificate of occupancy. Rental investors should not assume this exemption applies to their project.

Georgia’s mechanics and materialmen lien statute lists contractors, subcontractors, certain material suppliers, laborers and other qualifying parties who may have a special lien on improved real estate. See O.C.G.A. § 44-14-361. The claim is against the property, not only a personal claim against the party who hired them. A paid general contractor does not establish that each subcontractor or supplier has been paid. On priority, § 44-14-361.1(c) ranks these liens below taxes, below the general and special liens of laborers, below a landlord’s lien where a distress warrant has been issued and levied, and below purchase money claims, but above every other lien the subsection does not except.

A claim must be recorded in the county where the property is located within 90 days after completion of the work or after the materials are furnished, and the section makes the lien ineffective if any of its steps are skipped. The claim must contain the required expiration statement and notice of the owner’s right to contest, and a copy must be sent to the owner within two business days. A lien action must generally begin within 365 days after filing, with a notice of the action filed within 30 days after commencement. See O.C.G.A. § 44-14-361.1.

A lien filed after March 31, 2009 must carry, on its face in at least 12 point bold font, a statement that the claim expires and is void 395 days after filing if no notice of commencement of lien action is filed within that period. A claim without that statement is invalid. See O.C.G.A. § 44-14-367. Aggregate liens cannot exceed the contract price of the improvements, though that cap does not mean an unpaid claim disappears.

For projects covered by the notice-of-commencement provisions, the owner, agent or contractor must file the notice with the county superior court clerk no later than 15 days after physical work begins and post a copy on site. Certain parties without contractual privity must give the required notice to the contractor within the statutory period to preserve lien rights. Failure to file a notice of commencement makes that notice requirement inapplicable. See O.C.G.A. § 44-14-361.5.

How a waiver and affidavit of nonpayment work

A lien waiver signed before labor, services or materials are furnished is void under O.C.G.A. § 44-14-366. Georgia provides statutory interim and final waiver forms. A waiver is conclusively effective at the earliest of three moments: the claimant actually receives the stated funds, the claimant signs a separate written acknowledgment of payment in full, or 90 days pass after signing without an affidavit of nonpayment being recorded. The affidavit must be filed in the county where the property is located, with a copy sent to the owner within seven days. It suspends the waiver until full payment is received. Payment records and waivers should be matched to each contractor, subcontractor and supplier.

Worked hypothetical: separate scope, value and lien exposure

This example is hypothetical and is not a GPC listing. Assumptions: purchase price of $185,000, as-completed value of $245,000, and total scope of $42,000.

Budget line Items Total
Forcing bucket, subject-to conditions Roof $11,500; electrical service and panel $3,200; foundation piers $6,800; crawlspace seepage and vapor barrier $4,600 $26,100
As-is bucket, reported but not forced under the assumed facts LVP flooring $4,200; interior paint $3,400; cabinets and counters $3,900; appliances $2,600; landscaping $800; permits and dumpsters $1,000 $15,900
Total scope Both buckets $42,000

Ten percent of $245,000 is $24,500. The $26,100 forcing bucket exceeds that amount by $1,600, which is the figure an investor who has heard about the 10% rule tends to fixate on. The 10% ceiling belongs to qualifying postponed improvements in new or proposed construction, not to this existing-property rehab, so nothing here is capped at $24,500. What sets the $26,100 is the safety, soundness and structural test, and that test has no dollar limit. A 120% hold on the same number would be $31,320, but the cited escrow rule does not reach this transaction either.

At 75% loan-to-value, a value of $245,000 supports $183,750 before other loan limits and underwriting. If the same property appraises $9,000 lower at $236,000, the supported loan falls to $177,000. That is $6,750 less in proceeds for a scope decision that cost nothing at the closing table.

If the general contractor has been paid but two subcontractors remain unpaid, assume their claims total $14,700. Those claims may be asserted against the property if statutory requirements are met. The statute caps aggregate liens at the $42,000 contract price, not at the amount owed to those subcontractors. The cap is not a substitute for collecting payment evidence and waivers.

Scope checklist

  • Separate safety, soundness and structural deficiencies from reported as-is work.
  • Ask the lender which specific repairs require completion and what proof it accepts.
  • Confirm licensing and permit requirements for each scope and contractor.
  • Track payments and obtain statutory waivers after work or materials are furnished.
  • Calendar the notice-of-commencement and lien deadlines where applicable.
  • Set the renovation tolerance before the property is under contract, the way the GPC investment process treats it, and account for ownership costs such as landlord insurance.

Market context and next step

FMLS InfoSparks October 2026 data, verified November 20, reported Greater Atlanta months of supply at 5.0, the highest reading in its series back to January 2013. The sale-to-original-list ratio was 0.950, and the Greater Atlanta median sale price was $415,000. The FMLS InfoSparks Greater Atlanta data and Entire FMLS data provide the market context. In a market clearing at 95% of original ask with the loosest supply in thirteen years, an over-scoped rehab does not get rescued by the market. Related planning topics include Georgia property-tax appeals and Georgia deed types. For distressed-property context, see what a Georgia foreclosure purchase delivers after the auction.

Investor buyers can send buying criteria through the GPC Real Estate contact page, including target areas, price range, property type and renovation tolerance. GPC Real Estate buys in Fulton, DeKalb, Cobb, Gwinnett and Clayton counties.

Send the property address, asking price, photos, and access details to acquisitions@gpcrealestate.com.

General information about Georgia process, not legal, tax or investment advice, and a licensing question should go to the state board or a Georgia attorney.